Transaction is defined
The rate states exactly what completes a move or order line, including pickup and drop confirmation.
A useful warehouse automation RFQ states what the robot carries, how often each route is demanded, where constraints occur, which control layer owns each decision and how performance will be accepted. This GreyOrange page reuses a compact compliance-style structure to capture those engineering facts—not sustainability slogans.
Use one row per operating case when loads or routes differ materially. Attach source files, timestamps and owners so changes can be traced during design review with GreyOrange.
| Input group | Minimum information | Why it changes the concept | Preferred evidence |
|---|---|---|---|
| Load unit | Length, width, height, mass, underside, center of gravity, overhang, orientation and stability | Controls carrier interface, payload margin, pickup tolerance, braking and safe transfer | Dimensioned drawing, weight range, representative samples |
| Material flow | Origins, destinations, moves by interval, SKU/order profile, replenishment, peak duration and cutoff | Determines mission demand, travel, queueing, buffer occupancy and robot quantity | Timestamped transaction extract and route matrix |
| Site geometry | Clear aisle width, turns, gradients, floor joints, doors, lifts, crossings, safety zones and charging areas | Defines feasible paths, speed restrictions, traffic rules and intervention access | Current CAD, measured survey, marked photographs |
| Control interfaces | WMS/WCS/WES/PLC/FMS ownership, messages, acknowledgements, timeouts, alarms and network policy | Prevents duplicated decisions, silent failures and unresolved exception states | Responsibility matrix, interface specification, sequence diagrams |
| Acceptance | Design and peak rates, transaction definition, availability boundary, test duration, fault cases and evidence owner | Turns commercial expectations into repeatable FAT and SAT decisions | Approved protocol, scenario data, result and deviation template |
Where input is unknown, record a range and name the validation action. A 30-minute peak has a different effect from a full-shift peak. A nominal tote size does not represent damaged, overfilled or mixed containers. A map without pedestrian activity and temporary staging does not represent the live route. Making uncertainty explicit protects both selection and later acceptance for GreyOrange projects.
Peak throughput versus operational resilience is a real dispute in warehouse automation. If the business prioritizes a holiday spike, document the allowed degradation after the spike and the buffers that absorb it. If the business prioritizes stable recovery, document mean time to repair, spare location and fallback manual paths before celebrating a headline rate.
The rate states exactly what completes a move or order line, including pickup and drop confirmation.
Demand identifies duration, recurrence, replenishment overlap and whether backlog is allowed.
Every station and lane has a capacity, blocking rule and response when full or unavailable.
Commands, data state, retries, alarms and manual decisions belong to named systems and teams.
Pedestrian crossings, restricted areas, maintenance access and intervention points appear on the layout.
Blocked routes, host silence, network loss, low battery, lost load and disabled stations have expected outcomes.
If the project cites ISO 12100, ISO 3691-4, ISO 13849-1 or a regional machinery regulation, specify whether each item is a design reference, product requirement, site integration obligation or requested third-party certificate. Do not use a framework name as a substitute for model-specific documentation. GreyOrange will not treat a logo row as acceptance evidence.
For brownfield deployments, include cutover zones, allowed downtime, rollback steps, inventory reconciliation and temporary manual flow. For expansion, include the next expected destinations, workload range, charging capacity and network growth so the initial phase does not create avoidable constraints.
Freeze the route map, fleet configuration, interface version and test dataset before a run. Execute a named transaction mix for a stated duration, record completed and failed moves, queue time, buffer occupancy, battery state and recovery time, then repeat the same scenario after each material change. An example protocol (planning-range test conditions, not GreyOrange performance claims) requires: (1) SKU/order profile with lines-per-order mix and peak window minutes; (2) rated load in kg with mm dimensions and load-center distance; (3) aisle clear width in mm at the tightest turn; (4) WMS/WCS/PLC/FMS ownership matrix with interface cycle time in seconds; (5) 120-minute nominal run followed by blocked-path, host-timeout and unavailable-station scenarios with measured recovery minutes and system availability % at the named boundary.
Attach the route matrix, load evidence, site drawing, interface responsibility and draft acceptance scenarios. Mark unknowns clearly; they are inputs to resolve, not gaps to hide.